Calendar review fixes; working day hours setting

- Issues' estimated hours are spread over their working days from start to due date, instead of
  counted in full on both the start and due dates
- Tooltips in the two rightmost columns open leftward again (the rule targeted the old table layout)
- Today scrolls when today is on the page (the check read calendar values that don't exist)
- "Day N of M" on calendar cards and My Page skips holidays; My Page uses the user's date
- Each appointment's working days are worked out once per page (CustomerAppointment#working_days),
  and shared by placement, hours, day numbers and the end date
- The calendar toggles are kept in the session, so changing month loads the page once
- Clicking inside an open tooltip keeps it open; estimates load with the appointments
- Hours in a working day is a plugin setting (default 8)

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
This commit is contained in:
rickyandClaude Opus 5.5 committed 2026-11-02 21:12:31 -05:00
1 parent ae522baf63
commit 3a5d83aa69
12 files changed
+148 -187

No files matched your search

@@ -1,25 +1,7 @@
<%
non_working_days = Setting.non_working_week_days || []
app_datetime = (appointment.respond_to?(:date) && appointment.date.present?) ? appointment.date : appointment.start_date
start_date = app_datetime.to_date
target_date = day.to_date
# Which working day of the appointment this is (the calendar passes it; weekends and holidays skipped)
duration = [appointment.duration.to_i, 1].max
day_number = 0
if target_date >= start_date
date_cursor = start_date
working_count = 0
while date_cursor <= target_date
unless non_working_days.include?(date_cursor.cwday.to_s)
working_count += 1
end
if date_cursor == target_date
day_number = working_count
break
end
date_cursor += 1
end
end
day_number = local_assigns[:day_number] || appointment.working_day_number(day).to_i
%>
<%